I. overview:
according to Article 281 of the coal mine safety code, the joint commissioning of the underground main drainage pump system is carried out before the rainy season. The following measures are specially prepared and implemented after the approval of relevant leaders
II. Organization:
1. Commander in chief:
deputy commander in chief:
members:
2, -550 water pump room:
construction principal:
safety principal:
technical principal:
3, -450 water pump room:
construction principal:
safety principal:
technical principal:
4. Time: month, day, hour
III. relevant parameters of drainage system: (-450)
1. Total volume of original internal and external water tanks: 4179 cubic meters
volume of new external water tanks: 3400 cubic meters to stabilize the loading valve
total volume of water tanks: 7579 cubic meters
2, - 450m level. It is estimated that the normal water inflow is 130m3/h, and the maximum water inflow is 266m3/h
3, 1, 3, 4, 5 water pumps: D500 - 57 9
2 water pumps: D 10
4, drainage pipeline: Φ 32511 twice
5. Drainage height: 473.5m
6. Water pump Motor parameters:
the cost of components is 40% less than that of competitive multi-material 3D printers. Specification: d 9 specification: D 10
lift: 513m lift: 600m
flow rate: 500m3/h flow rate: 500m3/h
speed: 1480 RPM speed: 1480 RPM
shaft power: 862.5kw shaft power: 919.5kw
efficiency: 81% efficiency: 81%
drainage height: 473.5m drainage height: 473.5m
motor:
specification: yb630m power: 1 050kw
voltage: 6000V current: 118a
speed: 1484rpm manufacturer: Nanyang explosion proof motor factory
IV. relevant parameters of drainage system: (-550)
1, water pump 1 ~5: D 3
2, drainage pipeline: Φ 32511 two times
3. Drainage height: 100 meters
4. The normal water inflow at -550 level is expected to be 167m3/h, and the maximum water inflow is 303m3/h
water pump:
specification: D 3 lift: 171m
flow rate: 500m3/h rotational speed: 1480 RPM
shaft power: 287.5kw efficiency: 81%
drainage height: 100M
Motor:
specification: Yb power: 355KW
voltage: 6000V current: 40.6a
rotational speed: 1484rpm manufacturer: Jiamusi Motor Co., Ltd.
v. specific measures:
1. The water tank must be cleaned before the rainy season
2. The operation guarantee team and the sewage station of the mechanical and electrical department cooperate with each other to conduct a water test on the ground pipeline gate valve and two pipelines before the joint test run
3. The transportation assurance team and the pipe team cooperate with each other to inspect the drainage pipeline of the shaft twice
4. Comprehensively inspect all water pumps, high-voltage switchgear and high-voltage cables
5. The water pump, annular pipeline, water distribution gate valve, gate valve check valve, etc. in the pump room shall be overhauled by the transportation team to ensure that each pump is in good condition and that each pump can be started for drainage within 5 minutes
VI. construction method:
1, -550 water pump starts 1#~2# water pump uses one pipeline for drainage and 4#~5# water pump uses another pipeline for drainage; Conduct combined drainage of four pumps and two pipelines
2, -450 start 1#~ water pump to directly measure the radius and strain. 2 # water pump uses one pipeline to discharge water and 4 #~5# water pump uses another pipeline to discharge water; Conduct combined drainage of four pumps and two pipelines
3. During the joint test run, the driver on duty of the operation assurance team shall carefully observe and record the voltage, current, pressure and the time of starting and stopping the pump. The flow of the water pump is observed and recorded by the production office
4. The specific performance parameters of the water pump are tested by Anhui coal mine safety monitoring center, and formal test reports are provided
VII. Safety measures:
1. The water tank must be cleaned before the rainy season
2. The water pump and annular pipeline, water distribution gate valve, gate valve check valve and electrical equipment in the pump room shall be overhauled by the transportation team to ensure that the platform is in good condition
3. The drainage pipe of the shaft twice is in the charge of the pipe team
4. The mechanical and electrical department is responsible for the ground drainage pipeline and gate valve
5. During the joint test run, start all water pumps one by one, and it is forbidden to start at the same time
6. During the joint test run, the ground main hoist, auxiliary hoist and auxiliary shaft winches stopped running
7. The 35kV substation must monitor the current of 634 high-voltage switchgear in -450 pump room 631, the beam part of the electronic universal testing machine that cannot be moved, and 633 and 634 high-voltage switchgear in -550 pump room. If any abnormality is found, stop the joint test run immediately
8. Each water pump, motor and electric control equipment must be observed by a specially assigned person. In case of any abnormality, the operation shall be stopped immediately
9. During the joint test run, the commander in chief shall give the order, and the pump house shall be commanded by the person in charge of construction. It is strictly forbidden to command by more than one person